Case Study II | Distribution Warehouse

No comments

A fire occurred at a plastics distribution facility in Georgetown, Texas, requiring restoration services for the facility. The entire 40,000 sq-ft building was affected by fire and/or smoke. During the four month restoration, nearly 6000 sq-ft of the facility required new structural columns and beams as well as new 2×12 roof framing, miscellaneous block work and a new roof. The remainder of the structure was cleaned, dry ice blasted, and re-painted to mitigate the smoke damage.

The scope of work performed by All Nation Restoration exceeded $340,000 for this four month restoration project.